Albion was appointed to install a large mezzanine floor throughout the warehouse at Dragon Studios in Bridgend, creating additional usable space within the new production facility.
- Client
- Location
- Project Value
- Duration
- Albion Workforce
The Challenge
This was the largest mezzanine Albion had installed at the time, making it a significant project for the business and our installation team.
The scale of the installation required careful planning and coordination throughout the eight-week programme.

Our Approach
Albion installed a mezzanine floor covering the whole warehouse, providing a substantial additional level within the building.
The project was carefully planned and delivered over an eight-week programme.

The Result
The project was successfully completed, creating a significant additional floor area within Dragon Studios and contributing to the development of a new production centre in South Wales.
Are you ready to optimise your space?