The Brief

Albion was appointed to install a large mezzanine floor throughout the warehouse at Dragon Studios in Bridgend, creating additional usable space within the new production facility.

  • ClientDragon Studios
  • LocationBridgend, South Wales
  • Project Value£120k
  • Completed2022
  • Duration8 weeks
  • Albion Workforce6 employees

The Challenge

This was the largest mezzanine Albion had installed at the time, making it a significant project for the business and our installation team.  The scale of the installation required careful planning and coordination throughout the eight-week programme.

Our Solution

Albion installed a mezzanine floor covering the whole warehouse, providing a substantial additional level within the building.
The project was carefully planned and delivered over an eight-week programme.

dragon studios

The Result

The project was successfully completed, creating a significant additional floor area within Dragon Studios and contributing to the development of a new production centre in South Wales.

"Being part of the development of a new production centre in South Wales was something we were particularly proud of. It was also the largest mezzanine Albion had ever installed at the time."

Damien Freili

Managing Director, Albion Workplace Solutions