The Albion team collaborating in a modern office

The Brief

Albion was appointed to install a large mezzanine floor throughout the warehouse at Dragon Studios in Bridgend, creating additional usable space within the new production facility.

  • ClientDragon Studios
  • LocationBridgend
  • Project Value£120k
  • Duration8 weeks
  • Albion Workforce6 employees

The Challenge

This was the largest mezzanine Albion had installed at the time, making it a significant project for the business and our installation team.

The scale of the installation required careful planning and coordination throughout the eight-week programme.

Our Approach

Albion installed a mezzanine floor covering the whole warehouse, providing a substantial additional level within the building.

The project was carefully planned and delivered over an eight-week programme.

The Result

The project was successfully completed, creating a significant additional floor area within Dragon Studios and contributing to the development of a new production centre in South Wales.

Are you ready to optimise your space?

If you’d like expert advice about about an upcoming project, please contact us 

Get in touch today