Norgine Pallet Racking Installation
The Brief
Norgine required a large-scale pallet racking system for its facility in Oakdale, creating significant storage capacity ahead of the opening of the new facility in January 2026.
Albion worked closely with the client from the early stages of the project to help design and develop the storage solution around their requirements.
- Client
- Project Value
- Completed
- Duration
- Albion Workforce
The Challenge
The entire project had to be completed before Christmas, with the facility scheduled to open in January 2026.
This created a fixed completion deadline and required careful planning, coordination and programme management throughout the ten-week installation.

Our Solution
Albion supplied and installed a Link 51 pallet racking system providing more than 8,000 pallet positions, complete with wire mesh decks.
The project was developed around the client’s storage requirements, with Albion involved in helping to shape the solution before installation.

The Result
The project was successfully completed within the required timeframe, ready for the facility to open in January 2026.
"This was a particularly rewarding project because we weren't simply installing the racking. We worked with the client to help design and develop the solution around their requirements, then delivered the complete installation within a demanding programme."